Domestic

Case study

Guildford

Client: Private client
Purpose: Under pin on 2 sides of house
Ground Conditions: Soft Clay
Pile type: 76r
Depth: 7m
Quantity: 14
Additional work: Underpin brackets
Location: Guildford

The client had reports from conventional underpin companies they would have to move out for 6 months to carry out the works.

The preparation works were carried out for 6 days to enable screwpile and underpin bracket.

It took 3 days to install the piles and underpin brackets.

2 weeks to re-instate with even a new front porch with raft foundation on screwpiles.

The end result, amazing 1 month complete and client never left his house.

Releveant Case Studies

Below are some similar case studies we have worked on.

Civil
fill and chalk
89mm
Domestic
London Clay
89mm